0.1毫米,端面间隙沿圆周上的不同心度允差为0.1毫米,端面间隙沿圆周的不均匀允差0.3毫米(连接进出水管路后再分别校核一遍,仍符合上述要求)

    6、在检查电机转向与水泵的转向一致后,装上联轴器的联接柱销;

    7、不要把泵本身作为管路支撑点,管路应在泵的附近设可靠支撑。

    以上为不带底座的水泵机组的安装方法。

    对于配带公共底座的泵,基础与底座之间保留45毫米的间隙,用调整螺钉精确地调整机组并在联轴器处对中。其安装原则与不带公共底座的机组相同。

五、起动、停止和运行

    1、起动:

    1)、起动前的检查:

    a).泵或底座是否与基础紧固;

    b).联轴器与泵机组是否校正;

    c).管路是否按要求连接;

    d).手是否能容易地转动转子;

    e).是否所有轴承都有良好的润滑。

    2)、起动前关闭出口阀,用介质灌注排尽泵和管路内的空气。吸入状况时,用泵体上部的螺塞排气。在倒灌时泵也须排空;

2运行:

   1)、当压力表压力升高,慢慢打开出口阀;

   2)、打开所有辅助管路,并检查流量;

   3)、泵是填料密封运行时,填料还处允许有多少量,滴水,轻轻压紧填料压盖至少量滴水。

4)、为防止介质升温,泵不能在出口阀门

    5. After the concret solidifed, again correct the coaxial degree in the excircle of the two couplings, the error of the correction is not more than O.1 mm, the allowable error of the inhomo-geneous degree of the endface clearance along the circle is 0.3mm,  Re- inspect the correct pricision after tightening the foot unts,  finally, pour concret fuly nuder the foot of the pump and the motor except the around of the wedge shaped cushion.

    6. After check the rotary direction of the motor which is now in keeping with that of the pump,  you can install the connecting parallel pin of the coupling.

    7. The inlet pipe and outlet pipe should be supported by a brasket instead of the pump casing.

    Above all the mentioned methods and requirements are suitable for the pump set without common bedplate.

    Samely,  for the pump set with common bedplate. Fit the pre -assembled set with foun-dation bolts loosely inserted in the cut- outs in the foundation and align. There must be a 4-5cm gap between the top of the foundation and the bottom of the baseframe. Precisely align the set using the adjusting screws and check alignment on the coupling. Others you can refer to the above mention methods.

V. STARTING, STOPPING ADN RUNNING

     1. Starting:

     1 ). Before starting up the pump make sure that the following requirements have  been checked and fulfilled.

     a). Has the pump been firmly bolted to the base/foundation?

     b) . Have the coupling and pump unit been aligned as specified?

     c). Are the pipes properly fitted?

     d) . Can the unit be easily rotated by hand at the coupling? (Carry out at least one full rotation)

     e). Has lubrication been provided for oil-lubricated bearings?

     2)Before the pump is started up, it and the pipes must be vented and filled with the liquid to be pumped. In the case of both gravity feed and suction operation venting must be carried out via the hole on the upper suction elbow. In the case of suction operation the upum must